Status Update - 4/25/19
	    April 25, 2019
	
    | Status Item | Current Status | Previous Status | Comment | 
| Schedule | red | red | Banner Integration Delay | 
| Resources | green | green | |
| Financials | green | green | |
| Quality | green | green | |
| Project Issues | red | red | Banner/Axiom Integration data load is delayed | 
| Key Deliverables | % | Comments | Timeline | 
| Requirement Sign-off | 100% | 12/14 | |
| Data Model/Mapping | 100% | 1/12 | |
| Build | 99% | 4/19 | |
| Integration | 38% | Loaded: Accounts, Plans, Contacts, Address, Relationships, Affiliations, Terms | 5/3 | 
| Training/UAT | 0% | Training and UAT dates delayed | 5/14 | 
For the detailed April 25, 2019 status report, click here.